You are on PERI's international website. Click here to switch to PERI USA. Click here to view all PERI websites.

Los Ramones II Pipeline

Datos del proyecto

Ubicación: San Luis Potosi, México

45 square supports of 2.00 m in height with edge lengths from 40 cm to 50 cm

Requisitos

  • Reinforced concrete frame supports of a new control station for a gas pipeline
  • Quickly understood and with little training
  • Straightforward application

Cliente

RUBA Arquitectos, SA de CV, Mexico

Beneficio del cliente

  • The use of the innovative system formwork was extremely efficient and quick right from the beginning
  • Panels can easily be carried by hand
  • Easy to mount and move manually
  • Less crane times
  • Accelerated construction progress

Solución PERI

  • Utilization of the DUO Multi Panels
  • 5 sets of formwork are mounted with 4 DUO Multi Panels DMP 75 each
  • A circumferential PERI UP working scaffold with a ladder access
  • The instructions regarding the assembly, cleaning and storage were given by the PERI supervisor

Sistemas PERI utilizados